Legal Q&A · Construction & Development

Why are handover and a handover record important on a building project?

Law as at 10 September 2026

Short answer

Handover is important for performance of the works and generally also for the entitlement to payment. The transfer of ownership and risk of damage, however, depends on the contract and the regime under § 542 and § 554 of the Commercial Code; the employer may already own the works during construction. A warranty period is relevant if the contractor has assumed a quality warranty. At either party’s request, a written handover record must be made, recording identified defects and reservations.

What does handover mean?

The contractor fulfils its obligation by properly completing and handing over the works (§ 554(1) of the Commercial Code). Ownership and the risk of damage must, however, be assessed under the contract and § 542: where works are carried out on the employer’s land, the employer may already own them and bear the risk of damage during construction. If the contractor owned the completed item and § 554(5) applies, ownership passes to the employer on handover together with the risk of damage, unless that risk passed earlier. A quality warranty does not arise automatically from handover itself; if the contractor has assumed one, the running of the warranty is assessed under § 563 and the warranty agreement.

Is a handover record required?

If either party requests it, a written record signed by both parties must be made of the handover (§ 554(6)), known in practice as the handover record. It should include the condition of the works, identified defects and outstanding work, the agreed deadlines for remedying them and any reservations made by the employer. If the contract requires proper performance to be demonstrated by tests, the works are considered complete only once those tests have been passed, with a written record also being made (§ 555(2)).

Why does the handover record matter?

Without a record containing reservations, defects are difficult to prove after acceptance. Handover is relevant to the periods for notifying defects and, where a warranty has been assumed, also to the start of that warranty. The employer is also entitled to inspect the works during construction and require defective performance to be remedied (§ 550). The contractor’s entitlement to payment generally arises upon performance of the works (§ 548), so the handover date also affects payment.

Practical recommendation

We recommend agreeing the acceptance procedure in advance (dates, tests and the list of documents) and accepting the works with professional supervision to record defects. We arrange contracts and assistance at handover through legal services for construction companies and construction contracts; construction project coordination covers the technical and legal management of the project.

This answer provides general information on the law as at 10 September 2026. It does not constitute legal services or replace an assessment of an individual case. The details of your situation may differ. Book a consultation to discuss them.

More legal questions

All questions and answers
  1. Can a contractor charge more than the budget for additional works? It depends on how the price is agreed. If it is fixed or set by a budget, more demanding work does not itself change the price. If the contract states that the budget does not guarantee completeness, the contractor may seek a reasonable increase for unforeseeable activities, but must notify them without undue delay or lose the claim. An increase exceeding 10 % allows the employer to withdraw from the contract.
  2. How does an agreement to enter into a purchase contract work for flats in a development? In an agreement to enter into a future contract, the parties undertake in writing to conclude a purchase contract by an agreed date and must already agree its essential terms, especially the property and price. If one party fails to conclude it, the other may seek a court decision substituting for that party’s declaration of intent within one year, and also has a right to damages. In development projects, a reservation agreement usually comes first.
  3. As a developer, do I own the copyright in the design documentation? Design documentation is protected by copyright if it constitutes a unique result of creative intellectual activity. A technical document or its designation as design documentation does not in itself attract protection. For a protected design, the author is the designer or architect who created it through their own creative activity. Commissioning a design gives you a licence to use it for the purpose arising from the contract, not unlimited rights. Other uses, particularly building the same design again or having another designer alter it, require a specific agreement; moreover, the author’s economic rights cannot be transferred.
  4. What must a contract transferring a newly built flat contain? A contract transferring ownership of a flat must be written. Under the Flat Ownership Act, it must include in particular a description of the flat and its appurtenances, the co-ownership share in the building’s common parts and facilities and the land, arrangements for land rights, and the acquirer’s declaration of accession to building management. Ownership is acquired only through constitutive registration in the Land Register.

Cannot find your question? Ask your own question

Facing this situation?

Tell us what you need help with.

Describe your situation. We will review it and usually tell you within 24 hours whether and how we can help, including an indicative fee.

  1. 1Send your enquiry via this form
  2. 2Usually within 24 h you get a price confirmation and plan
  3. 3We start work only after your approval
Mgr. Patrik Tulinský, LL.M. Czech and Slovak attorney · SAK 300422 · ČAK 19654

Not keen on calls or email? Message us on WhatsApp →
Prefer to book a time right away? Book a consultation →
Or email us about this matter.

PDF, Word, images, ZIP… max 10 MB per file, 30 MB total.

Submitting this form does not create an engagement or attorney-client relationship. Before taking on a matter we run a conflict-of-interest check, so please do not send sensitive originals until we confirm the matter together.

Contact a lawyer