Legal Q&A · Construction & Development

Why are handover and a handover record important on a building project?

Law as at 10 September 2026

Short answer

Handover is important for performance of the works and generally also for the entitlement to payment. The transfer of ownership and risk of damage, however, depends on the contract and the regime under § 542 and § 554 of the Commercial Code; the employer may already own the works during construction. A warranty period is relevant if the contractor has assumed a quality warranty. At either party’s request, a written handover record must be made, recording identified defects and reservations.

What does handover mean?

The contractor fulfils its obligation by properly completing and handing over the works (§ 554(1) of the Commercial Code). Ownership and the risk of damage must, however, be assessed under the contract and § 542: where works are carried out on the employer’s land, the employer may already own them and bear the risk of damage during construction. If the contractor owned the completed item and § 554(5) applies, ownership passes to the employer on handover together with the risk of damage, unless that risk passed earlier. A quality warranty does not arise automatically from handover itself; if the contractor has assumed one, the running of the warranty is assessed under § 563 and the warranty agreement.

Is a handover record required?

If either party requests it, a written record signed by both parties must be made of the handover (§ 554(6)), known in practice as the handover record. It should include the condition of the works, identified defects and outstanding work, the agreed deadlines for remedying them and any reservations made by the employer. If the contract requires proper performance to be demonstrated by tests, the works are considered complete only once those tests have been passed, with a written record also being made (§ 555(2)).

Why does the handover record matter?

Without a record containing reservations, defects are difficult to prove after acceptance. Handover is relevant to the periods for notifying defects and, where a warranty has been assumed, also to the start of that warranty. The employer is also entitled to inspect the works during construction and require defective performance to be remedied (§ 550). The contractor’s entitlement to payment generally arises upon performance of the works (§ 548), so the handover date also affects payment.

Practical recommendation

We recommend agreeing the acceptance procedure in advance (dates, tests and the list of documents) and accepting the works with professional supervision to record defects. We arrange contracts and assistance at handover through legal services for construction companies and construction contracts; construction project coordination covers the technical and legal management of the project.

This answer provides general information on the law as at 10 September 2026. It does not constitute legal services or replace an assessment of an individual case. The details of your situation may differ. Book a consultation to discuss them.

More legal questions

All questions and answers
  1. We demolished a building. How do we remove it from the title sheet if it is mortgaged? It is not removed automatically. Removing a building is a change to cadastral data made at the owner’s request and supported by evidence, usually a municipal confirmation of demolition and a survey plan. A mortgage terminates when all the assets it covers cease to exist, but its entry is not deleted automatically either. If the loan remains outstanding, the bank will usually require replacement security, so speak to it before demolition, not afterwards.
  2. We want to extend our flat into the loft. Is consent at the owners’ meeting enough? No. If alterations change the size of a flat, non-residential premises or appurtenances at the expense of common parts or facilities, the person carrying out the project must define reciprocal rights and obligations in a contract with the other owners of flats and non-residential premises in the building. The contract and its amendments are registered in the Land Register, supported by documentation showing the area and location of the premises.
  3. An old house has no occupancy approval and is absent from the Land Register. How do I register it? It depends on when it was built. Since 1 April 2024, the law treats a house built before 1 October 1976 as lawful without further requirements. For houses from 1976 to 1989, continuous use for their intended purpose and the owner’s ownership or other right to the land on 1 April 2024 are required. Registration is not automatic: apply with a municipal notice, a survey plan and, for the later buildings, evidence of land rights.
  4. We built without a building permit in the 1990s. Can the building still be legalised? Usually yes. On the owner’s application, the building authority reviews a building erected and used without permission between 1 January 1990 and 31 March 2025 and, if statutory conditions are met, issues a decision with the effects of occupancy approval. Applications are possible only until 31 March 2029, and the conditions are substantive: if they are not proved, the authority orders demolition. It is therefore worth assessing prospects before approaching the authority.

Cannot find your question? Ask your own question

Facing this situation?

Tell us what you need help with.

Describe your situation. We will review it and tell you within 24 hours whether and how we can help, including an indicative fee.

  1. 1Send your enquiry via this form
  2. 2Within 24 h you get a price confirmation and plan
  3. 3We start work only after your approval
Mgr. Patrik Tulinský, LL.M. Czech and Slovak attorney · SAK 300422 · ČAK 19654

Not keen on calls or email? Message us on WhatsApp →
Prefer to book a time right away? Book a consultation →
Or email us about this matter.

PDF, Word, images, ZIP… max 10 MB per file, 30 MB total.

Submitting this form does not create an engagement or attorney-client relationship. Before taking on a matter we run a conflict-of-interest check, so please do not send sensitive originals until we confirm the matter together.