It depends on how the price is agreed. If it is fixed or set by a budget, more demanding work does not itself change the price. If the contract states that the budget does not guarantee completeness, the contractor may seek a reasonable increase for unforeseeable activities, but must notify them without undue delay or lose the claim. An increase exceeding 10 % allows the employer to withdraw from the contract.
Is a budget-based price binding?
Under § 547 of the Commercial Code, the price is not affected by having been determined on the basis of a budget (paragraph 1): a budget alone does not mean the price may change. What matters is how the contract characterises the budget:
- if the budget does not guarantee completeness, the contractor may seek a reasonable increase where performance reveals a need for activities omitted from the budget that were not foreseeable when the contract was concluded (paragraph 2),
- if the budget is non-binding, the contractor may seek an increase by the amount by which its efficiently incurred costs necessarily exceed those included in the budget (paragraph 3),
- if the employer disagrees with the increase, the court determines its amount on the contractor’s application (paragraph 4).
When does the contractor lose its claim for additional works?
The contractor loses its entitlement to a price increase if it fails to notify without undue delay the need to exceed the budget and the amount of the increase sought after the need for the overrun becomes apparent (§ 547(6)). The employer should also take care: if the contractor seeks an increase exceeding 10 % of the budgeted price, the employer may withdraw from the contract without undue delay and pay only the portion corresponding to the work performed (paragraph 5).
What if the scope of the works changes?
If, after concluding the contract, the parties agree to extend, reduce or alter the works without agreeing the effect on price, the price increases or decreases reasonably according to the difference in the scope of activities and efficiently incurred costs (§ 549). Additional works should therefore always be approved by a written amendment.
Practical recommendation
We recommend stating clearly whether the price is fixed or budget-based and adding a clause governing approval of additional works and changes. We prepare contracts through legal services for construction companies and construction contracts; for larger projects, we also connect these arrangements with development project finance.
This answer provides general information on the law as at 21 July 2026. It does not constitute legal services or replace an assessment of an individual case. The details of your situation may differ. Book a consultation to discuss them.