Litigation and compensation · Slovakia
Disputes over defective work
The work has defects that nobody is fixing. The contractor has not completed what was promised. The client refuses acceptance and pays neither the price nor the variations. We review the contract, site diary, records and correspondence with you, establish what will stand up in court and tell you frankly whether the dispute is worth pursuing.
- For clients and contractors
- Evidence assessed before filing
- Lawyer registered with the Czech and Slovak Bar Associations
What we'll do for you
Assessment of a works dispute and representation for the client or contractor, from reconstructing evidence through negotiation to court proceedings.
Select an item to see the details.
-
Reconstructing the evidence trail
We review the contract, site diary, work schedules, records, photographs and correspondence and build a timeline of what actually happened and what you can prove.
-
Assessment of handover and defect notices
We check whether the work was properly handed over and accepted, whether and when the right to payment arose, and whether defects were notified specifically, in time and to the correct recipient. These are the points on which disputes most often fail.
-
Choosing and calculating the claim
For defects, we choose the remedy that makes sense in your situation — rectification, a price reduction, repair by a third party or damages. We calculate the price, variations, penalties and retention, eliminating duplication.
-
Out-of-court negotiation
Where it makes sense, we attempt a settlement or an agreement on completion and financial settlement. This is often faster and cheaper than years of litigation involving experts.
-
Court claim, defence and expert evidence
If agreement is impossible, we prepare the claim or defence and represent you in proceedings. We do not assess the technical aspects of defects ourselves — we are not experts; we arrange an expert in the relevant field, propose their appointment to the court and frame questions that address what matters in your dispute.
Deliverableassessment of the dispute, an agreed strategy and representation through to its conclusion
We tailor the scope to the matter. Sometimes an assessment and one negotiation suffice; other cases involve years of litigation with expert evidence. We agree the approach and price in advance.
How it works
Does this process fit your matter? Describe it to the attorney →
- Case-file assessmentday 0
We review the documentation and tell you frankly how strong your position is, what evidence is missing and what can still be obtained.
- Strategy and claim
We choose a remedy and approach, assert it through a demand or defect complaint, and attempt an out-of-court resolution. At the same time, we prepare the documents for possible litigation.
- Disputesubject to the court's timetable
We bring or defend the claim, arrange an expert and conduct the evidence phase; we see the dispute through — if successful, all the way to actual payment.
No-obligation enquiry
Ready to start?
Send us an enquiry. We reply within 24 hours with a price confirmation and next steps. The first 30-minute consultation is free and commits you to nothing.
- 1Send your enquiry via this form
- 2Within 24 h you get a price confirmation and plan
- 3We start work only after your approval
Not keen on calls or email? Message us on WhatsApp →
Prefer to book a time right away? Book a consultation →
Or email us about this matter.
What clients ask
Didn’t find your question? Ask us directly →
When does the contractor become entitled to the price of the work?
Under Commercial Code No. 513/1991 Coll. (particularly § 548 and § 554), entitlement to the price is linked to performance of the work, generally its proper completion and handover — not merely issuing an invoice. That is why a price dispute often turns on whether the work was completed and delivered, and what the documentation shows. If the client obstructs acceptance, you must be able to prove it.
The client refuses to accept the work. What can be done?
We first examine what the contract says about arranging handover, reservations and minor defects or incomplete items — and whether the reason for refusal is justified. The distinction between a defect preventing use and a cosmetic unfinished item is often decisive. We also ensure your invitation to accept the work, record of refusal and photographic evidence are produced promptly and verifiably.
How and by when must defects be notified?
Defects must be notified specifically, promptly and to the correct recipient — a general statement that you are dissatisfied is insufficient; the description must identify the precise complaint. The law requires the client to inspect the work or arrange an inspection as soon as possible after handover; if defects are not notified without undue delay after they were discovered or should have been discovered with professional care, the court will not award the defect claim if the contractor raises that objection, subject to the statutory exception where the contractor knew of the causes of the defect (§ 562 read with § 428(2) and (3) of the Commercial Code). The point at which time starts running is often crucial: in a dispute over defective agricultural work, the Regional Court in Banská Bystrica held that the duty to notify defects arose only after the entire subject of the work was delivered, and treated the sampling and professional assessment arranged after handover as arranging an inspection; the Supreme Court of the Slovak Republic left that decision undisturbed when it rejected the contractor's appeal on points of law (5Obdo/5/2024, order of 25 March 2025). We therefore begin by checking what you notified, when and to whom — and whether this complies with the contract and law.
We missed the defect notification deadline. Is everything lost?
Not necessarily. § 428(2) and (3) of the Commercial Code apply by analogy to the effects of late notification (§ 562(3)). In simple terms, the contractor cannot rely on a late complaint where the defects arise from circumstances it knew or must have known about at handover. This was also central to the dispute mentioned above — the defects resulted from the contractor's incorrect technical procedure. Whether the exception applies to your situation depends on the evidence of what the contractor knew; it is nevertheless a reason not to give up as soon as late notification is raised.
Must the client pay for variations it did not approve in writing?
If the contract requires a written change order for a scope change and none exists, the contractor's position is significantly weaker — entitlement to additional payment often turns on whether another agreement or legal basis can be proved. This does not apply automatically in every case, however: the contract's wording, the parties' actual conduct during performance, and what the diary and correspondence say about changes all matter. We assess these documents first.
How much does such a dispute cost, and how long does it take?
Frankly, works disputes are among the longer and more expensive cases. In addition to the court fee and lawyer's fees, allow for an advance payment for an expert, usually essential on questions of quality and the price of work, and for proceedings that may last years. We therefore first assess the strength of the evidence and the recoverability of the claim against the other party, and tell you if we consider litigation not worthwhile. We confirm the price of each phase in advance; nobody can promise the outcome.
Legal Q&A
Common questions on this topic
-
How do defect liability and warranties work under a construction contract?
A construction contract between businesses is governed by the Commercial Code. The contractor is liable for defects present at handover. The employer must notify defects without undue delay after discovering them or when they should have been discovered, and within five years of handover for buildings. If a quality warranty is agreed, the warranty period replaces this period. Late notification does not, however, automatically extinguish the rights: the court considers the contractor’s objection, and the Act provides an exception where the contractor knew the cause of the defect.
Read the answer -
The customer is using the works but has not signed the handover record and refuses to pay. What can we do?
The precise wording of the agreement is decisive. If signing a handover record is agreed as a condition of handing over the works, courts have long held that without it the works have not been handed over and no entitlement to the price has arisen, even if the customer uses them. In 2025, Czech case law began denying protection to parties invoking the agreed form dishonestly; Slovak courts have not yet adopted that shift. New agreements should therefore include deemed handover.
Read the answer -
The works are defective. Can we claim damages as well as a price reduction?
Yes, but the claims must be kept distinct. What can be obtained through defect remedies, such as repair, a price reduction or replacement performance, cannot be claimed again as damages. Consequential losses not covered by the reduction, such as profits lost during production downtime or costs caused by the defect in dealings with your customers, are claimed separately as damages. Note the statutory limit: a price reduction excludes lost profits arising from the very missing characteristic to which the reduction relates.
Read the answer
Further reading
Work statements, interim invoices and retention: construction payments depend on the contract
When a contractor gets paid depends on the contract’s billing arrangements: statements of completed work, approval and retention. Set them up so payments continue throughout construction and the first disagreement does not stop cash flow.
Read more →
Acceptance records in contracts for work: the formality that determines payment
Contractors generally do not get paid until handover, and the contract defines what handover means. How to agree acceptance records, deemed acceptance and acceptance with minor defects, and how Slovak and Czech case law treats withheld signatures.
Read more →
Breach of contract under the new rules: one system of remedies
The new Civil Code is intended to unify remedies for breach across all contract types. Today, they must be found in incomplete rules for individual contracts, often in two different codes. What this changes for clauses in your templates.
Read more →