Legal Q&A · Construction & Development

We built exactly to the employer’s design and the works are defective. Are we liable?

Law as at 5 September 2026

Short answer

Yes, if you failed to warn that the design or instructions were unsuitable although professional care would have revealed this. The defence “we followed the design” is not enough: the Commercial Code exempts a contractor only where it warned the employer, who then insisted in writing on using the items or instructions. Work must be suspended as necessary until the employer decides. A provable warning and the employer’s written insistence are therefore crucial; the site diary is the natural place to record them.

“We merely followed the design” is the contractor’s most common defence in a defects dispute, and it is insufficient on its own in court. The Commercial Code (Act No. 513/1991 Zb.) protects a contractor that spoke up, not one that built in silence.

Contractors are professionals and must speak up

The contractor must warn the employer without undue delay of unsuitable items received from it and instructions it gave, including design documentation, if professional care would have revealed their unsuitability. If unsuitable items or instructions prevent proper performance, work must be suspended to the necessary extent until the items are replaced, the instructions changed or the employer confirms in writing that it insists on them. The completion period is extended by the suspension, and the contractor is entitled to reimbursement of the related costs (§ 551(1) of the Commercial Code).

When you are not liable for defects

A contractor that has fulfilled the obligation under paragraph 1 is not liable for inability to complete the works or for defects in completed works caused by unsuitable items or instructions where the employer insisted in writing on their use in performing the works.

— § 551(2) of the Commercial Code (unofficial translation)

Exemption requires two conditions: you gave a warning, and the employer nevertheless insisted on use in writing. A contractor that gave no warning is liable for defects caused by unsuitable items or instructions (§ 551(3)). A contractor also avoids liability if even professional care could not have revealed the unsuitability, for example a hidden error in structural calculations that a construction company could not detect (§ 561).

What makes a warning stand up as evidence?

The law does not prescribe the warning’s form, but the contractor bears the burden of proof, and the employer’s insistence must expressly be in writing. Oral discussions at a site meeting are therefore insufficient in a dispute. A tried and tested approach is to enter the warning in the site diary and also send it by letter or email with confirmation of delivery, identify precisely what is unsuitable and the likely consequences, and ask the employer to decide. If the employer insists on the original solution, request a written statement; do not restart the affected work until it is provided. Email is usable evidence if you can prove sending and who acted on behalf of the sender; with contentious employers, a letter with proof of delivery or a signature in the diary is more reliable.

Our disputes experience is clear: what matters is what was recorded and delivered, not what the parties remember.

Remember the employer’s defect notification deadlines

If the employer nevertheless raises defects, it must meet the applicable deadlines: notification without undue delay after discovering them or when they should have been discovered, and within two years, or five years for buildings, of handover (§ 562). We explain defect remedies and warranties in construction contracts in our answer on defects and warranties under a construction contract.

How we can help

We structure your construction contract to give warnings, work suspension and variations clear procedures and records. In an existing dispute, we assess whether the warning and the employer’s insistence stand up as evidence and handle the defective works dispute. We maintain construction companies’ documentation and procedures through ongoing legal services for construction companies.

If you are currently facing an unsuitable instruction from the employer, contact us before carrying it out: a warning cannot be written retrospectively.

This answer provides general information on the law as at 5 September 2026. It does not constitute legal services or replace an assessment of an individual case. The details of your situation may differ. Book a consultation to discuss them.

More legal questions

All questions and answers
  1. We built without a building permit in the 1990s. Can the building still be legalised? Usually yes. On the owner’s application, the building authority reviews a building erected and used without permission between 1 January 1990 and 31 March 2025 and, if statutory conditions are met, issues a decision with the effects of occupancy approval. Applications are possible only until 31 March 2029, and the conditions are substantive: if they are not proved, the authority orders demolition. It is therefore worth assessing prospects before approaching the authority.
  2. The authority returned our minor-building notification. Can we challenge this? Yes. Returning a notification is not a decision, so an ordinary appeal is unavailable. However, Act No. 25/2025 Z. z. allows the applicant to request a review of the administrative authority’s procedure. The request must reach the appellate authority within 10 working days of delivery of the returned notification and include the notification as originally submitted. If the procedure was incorrect, the notification is returned to the authority with instructions to process it.
  3. We bought a house in a heritage zone. What can we do without involving the heritage authority? Less than people expect, depending on the regime. For a house in a heritage area, a regional heritage authority decision approving the proposed alteration is needed before new construction or alterations, even if the house itself is not a monument. In a buffer zone, a binding opinion is required instead; for a cultural monument, a decision on the restoration proposal is required. The common rule is: obtain the decision on the proposal first, then commission the design.
  4. Do we have to arrange supervision by the designer during construction? And what about the architect’s author’s supervision? Yes. The Building Act obliges the builder to arrange design supervision by the designer while the building is being constructed, and continuous supervision in the case of reserved buildings. Alongside it, the author of the architectural work has its own entitlement to carry out author’s supervision, even where the building design is prepared by another designer. The Act does not, however, say to what extent and for what fee the supervision is carried out; that must be set out in the contract with the designer and with the architect.

Cannot find your question? Ask your own question

Facing this situation?

Tell us what you need help with.

Describe your situation. We will review it and usually tell you within 24 hours whether and how we can help, including an indicative fee.

  1. 1Send your enquiry via this form
  2. 2Usually within 24 h you get a price confirmation and plan
  3. 3We start work only after your approval
Mgr. Patrik Tulinský, LL.M. Czech and Slovak attorney · SAK 300422 · ČAK 19654

Not keen on calls or email? Message us on WhatsApp →
Prefer to book a time right away? Book a consultation →
Or email us about this matter.

PDF, Word, images, ZIP… max 10 MB per file, 30 MB total.

Submitting this form does not create an engagement or attorney-client relationship. Before taking on a matter we run a conflict-of-interest check, so please do not send sensitive originals until we confirm the matter together.

Contact a lawyer