Do we have to arrange supervision by the designer during construction? And what about the architect’s author’s supervision?

Law as at 12 September 2026

Short answer

Yes. The Building Act obliges the builder to arrange design supervision by the designer while the building is being constructed, and continuous supervision in the case of reserved buildings. Alongside it, the author of the architectural work has its own entitlement to carry out author’s supervision, even where the building design is prepared by another designer. The Act does not, however, say to what extent and for what fee the supervision is carried out; that must be set out in the contract with the designer and with the architect.

An investor holding a verified building design and a selected contractor often regards the designer’s work as finished. The new Building Act (Act No. 25/2025 Coll.) takes a different view: the designer accompanies the building through to occupancy approval, and the builder is obliged to arrange its supervision. If the contract with the designer does not address supervision, the investor discovers on site either that there is no one to carry it out, or that the designer invoices it as additional work.

What the Act requires

Among the builder’s duties is to arrange, while the building is being constructed, design supervision by the designer over the construction of the building (Section 30(4)(d) of the Building Act). For a reserved building the Act requires more: the supervision must be continuous, and the designer also checks the structural safety of the ancillary load-bearing structures (Section 30(5)(c)). The designer must attend any inspection to which it is invited because of a need to change the design or to substitute construction products, and it records in the site diary any departures from the design that it finds unremedied (Section 35(7)).

The key provision on supervision also states what the designer is not liable for:

While the building is being constructed, the designer is entitled to carry out on the site supervision by the designer over the construction of the building as regards conformity of the construction work with the building design; this is without prejudice to the entitlement of the author of the architectural work to carry out supervision over the construction of the building as regards conformity of the construction work with its proposal (hereinafter ‘author’s supervision’). The designer is not liable for changes and departures from the verified building design that it has not approved and that occurred while the building was being constructed.

— Section 35(10) of Act No. 25/2025 Coll. (unofficial English translation)

The second sentence has a practical consequence for the investor. The designer is not liable for a change made on site by the contractor without its approval. Where supervision has not been agreed and no one approves the changes, the investor faced with a later defect can as a rule turn only to the contractor, and must prove to it that the defect was caused by precisely that unapproved change.

How the designer’s supervision differs from author’s supervision

Supervision by the designer monitors whether the construction follows the verified building design. Author’s supervision belongs to the author of the architectural work, typically the architect who designed the study, and monitors conformity of the building with its proposal. Both have statutory access to the site (Section 38(2)(c) and (d)) and the right to make entries in the site diary (Section 39(2)(a) and (h)). The Act on authorised architects lists author’s supervision among the services of an architect who is the author of the work (Section 4(e) of Act No. 138/1992 Coll.).

For a developer this means that the architect retains its entitlement to author’s supervision even where the building design was elaborated after the study by another designer. If the contract with the architect does not determine the extent of the author’s supervision and the fee for it, two persons with differing views of what is still in conformity with the proposal may meet on site.

What to agree in the contracts

As regards supervision by the designer, we recommend specifying in the design documentation agreement in particular:

  • whether the supervision is included in the price of the design or paid separately (as a lump sum or by inspection days actually carried out),
  • the minimum scope: attendance at inspections, the frequency of site visits, the period for responding to a change proposed by the contractor,
  • the procedure for approving changes, ideally by an entry in the site diary, and how this connects to an extraordinary inspection under Section 43(2),
  • what happens to the supervision if you terminate the contract with the designer before construction begins.

As regards the architect, the architectural study agreement should contain an agreement on whether author’s supervision is being ordered, who pays for it and how to deal with the architect’s disagreement with a change that the investor and the designer consider necessary. The licence and consent to alterations of the work are also connected with the question of copyright in design documentation.

If the contracts are already signed and supervision is missing from them, it can be added by an amendment before construction work begins. We prepare it so that it dovetails with the construction contract with the contractor and with the construction schedule.

This answer provides general information on the law as at 12 September 2026. It does not constitute legal services or replace an assessment of an individual case. The details of your situation may differ. Book a consultation to discuss them.

More legal questions

All questions and answers
  1. Why are handover and a handover record important on a building project? Handover is important for performance of the works and generally also for the entitlement to payment. The transfer of ownership and risk of damage, however, depends on the contract and the regime under § 542 and § 554 of the Commercial Code; the employer may already own the works during construction. A warranty period is relevant if the contractor has assumed a quality warranty. At either party’s request, a written handover record must be made, recording identified defects and reservations.
  2. How does an agreement to enter into a purchase contract work for flats in a development? In an agreement to enter into a future contract, the parties undertake in writing to conclude a purchase contract by an agreed date and must already agree its essential terms, especially the property and price. If one party fails to conclude it, the other may seek a court decision substituting for that party’s declaration of intent within one year, and also has a right to damages. In development projects, a reservation agreement usually comes first.
  3. As a developer, do I own the copyright in the design documentation? Design documentation is protected by copyright if it constitutes a unique result of creative intellectual activity. A technical document or its designation as design documentation does not in itself attract protection. For a protected design, the author is the designer or architect who created it through their own creative activity. Commissioning a design gives you a licence to use it for the purpose arising from the contract, not unlimited rights. Other uses, particularly building the same design again or having another designer alter it, require a specific agreement; moreover, the author’s economic rights cannot be transferred.
  4. What must a contract transferring a newly built flat contain? A contract transferring ownership of a flat must be written. Under the Flat Ownership Act, it must include in particular a description of the flat and its appurtenances, the co-ownership share in the building’s common parts and facilities and the land, arrangements for land rights, and the acquirer’s declaration of accession to building management. Ownership is acquired only through constitutive registration in the Land Register.

Cannot find your question? Ask your own question

Facing this situation?

Tell us what you need help with.

Describe your situation. We will review it and usually tell you within 24 hours whether and how we can help, including an indicative fee.

  1. 1Send your enquiry via this form
  2. 2Usually within 24 h you get a price confirmation and plan
  3. 3We start work only after your approval
Mgr. Patrik Tulinský, LL.M. Czech and Slovak attorney · SAK 300422 · ČAK 19654

Not keen on calls or email? Message us on WhatsApp →
Prefer to book a time right away? Book a consultation →
Or email us about this matter.

PDF, Word, images, ZIP… max 10 MB per file, 30 MB total.

Submitting this form does not create an engagement or attorney-client relationship. Before taking on a matter we run a conflict-of-interest check, so please do not send sensitive originals until we confirm the matter together.

Contact a lawyer